US firm pips BiFab to secure share of offshore wind order


By Douglas Fraser
Business and economic system editor, Scotland

picture copyrightBOWL

picture captionThe rising quantity of wind generators of Scotland’s coast have usually failed to ship advantages to Scottish producers

The battle to secure manufacturing orders for Scottish corporations looking for a share of offshore wind orders has suffered a extreme blow.

BiFab, with two yards in Fife and one close to Stornoway, failed to win any of the work for the Seagreen array being constructed off the east of Fife.

All of the platforms for its 114 generators are being manufactured in China and the United Arab Emirates.

The contract was introduced by profitable bidder Texas-based Fluor Corporation.

The choice adopted months of planning to secure at the very least some of the work for the mothballed yards at Methil and Burntisland.

They had been

saved from everlasting closure in April 2018, in a rescue bundle led by Canadian firm DF Barnes, with a stake taken by the Scottish authorities.

picture copyrightGetty Images
picture captionBiFab’s Methil yard in Fife had hoped to secure some of the work.

A press release by DF Barnes the choice was”extraordinarily disappointing”, a “missed alternative for Scotland and a matter of deep remorse”.

It added: “Since buying BiFab we have now been attempting exceptionally arduous to get individuals again to work in our yards.

“Instead Scottish and Southern Energy (SSE), within the face of what may very well be one of the worst recessions in trendy historical past, has chosen to give all of the fabrication work for one of the most important offshore windfarm initiatives on this planet to firms in China and UAE.”

But an business insider accused DF Barnes of failing to put any funds behind its bid – both in bettering the Fife yards or in offering monetary ensures that it might ship on time.

Trade unions have been extremely crucial of the failure to secure extra engineering work in offshore renewable energy.

GMB official Hazel Nolan mentioned: “We warn business majors like SSE and the governments at Holyrood and Westminster that fixed disappointment is now turning to rising anger – our communities depending on offshore wind fabrication contracts are being completely failed, and so is the nation”.

picture copyrightKen Jack/Getty Images

SSE Renewables, a division of the Perth-based vitality firm growing the Seagreen wind array, mentioned it had labored arduous to guarantee some of the work went to a Scottish contractor, however blamed the value hole between the Chinese and the Fife yards.

A spokesman mentioned: “We wished nothing greater than to award work to a Scottish firm that will assist set them up for future success.

“Unfortunately, on this event, the hole between BiFab’s providing and that of competing fabricators was too important to shut”.

He added the choice was additional proof that the business and authorities want to step up efforts to construct “an investable, globally aggressive UK provide chain”.

The BiFab yards equipped platform jackets for the oil business, they usually had been seen as the most effective hope in Scotland for fabricating the platforms for offshore wind generators.

But repeatedly, contracts have gone to abroad yards, together with Spain, Indonesia, the UAE and now China.

Overseas yards are in a position to construct at scale and with costs far decrease than BiFab can obtain. They can also achieve from authorities subsidy.

The primary Chinese fabrication yard getting used for Seagreen platforms completes a wind farm jacket each 10 days.

DF Barnes remains to be negotiating a couple of contract for fabrication work as half of the NnG (Neart na Gaoithe) wind farm being developed off the Firth of Forth by French vitality firm EDF, and mentioned it hopes to make “a optimistic announcement shortly”.